Prepared for Elm Inc. — prime contractor to the Orphan Well Association — by Innovative Well Abandonment. Hydrojet cut and cap services on the Revitalize Energy orphan inventory inside 30 km of Lloydminster, across a Fall 2026 and a Winter 2027 execution window.
A dense orphan inventory inside a 30 km radius of Lloydminster — the shortest possible move between wells.
A uniform string across the program — standard Lloydminster surface and production casing, no conductor barrels.
| Phase | Execution Window | Wells | Ready Now | Notes |
|---|---|---|---|---|
| Phase 1 — Fall 2026 | Mid-September 2026 onward | 85 | 60 | 60+ wells ready to cut and cap today; 85 anticipated advanced by mid-September. |
| Phase 2 — Winter 2027 | Mid-February – March 2027 | 50 | — | Winter-access-only locations following an unseasonably wet summer. |
| Total Program | 135 | 60 | 244.5 mm surface / 177.8 mm production · no conductors | |
Source: Elm Inc. — RFQ: Cut and Cap, OWA 2026 Well Abandonments (v1.1). Well counts per Elm's stated program scope; final list to be confirmed on award.
No flame. No hot work. Controlled sub-grade cut, vented cap, and a restored surface on every well.
Hydrojet cut and cap on 135 orphan wells belonging to Orphan Well Association (Revitalize Energy Inc.) in the Lloydminster field. Each well includes removal and disposal of the wellhead, installation of the vented cap, and backfill of the excavation — quoted as a single all-in rate. Execution starts mid-September 2026 with a second round in mid-February to March 2027.
High-pressure water-abrasive cutting on the wellhead — eliminates ignition risk entirely. Clean kerf, repeatable depth, no heat-affected zone, and minimal to no ground disturbance required.
Vented cap supplied and installed to regulatory standard immediately following the cut, with photo documentation and cap details recorded per well for the OWA file.
All cut wellheads loaded, manifested, and hauled off location for disposal — included in the all-in well rate, with the dump trailer available as an as-required line item.
Excavation backfilled and compacted with the rubber-tire backhoe before the crew leaves location. Surface left tidy for the reclamation program that follows.
65 wells cut within 100 km of Lloydminster across the three completed June–May operating periods.
Elm's minimum is 8 wells per 12-hour period. IWA's measured cycle times on comparable no-conductor programs leave meaningful headroom.
Equipment, experience, and safety systems behind the program.
Award, onboarding, two execution rounds, and a clean close-out package for the OWA.
Structured line-for-line against the Elm Inc. pricing request.
Regardless of casing or wellhead size.
Cut wellheads moved to the steel-field dumpster.
No overtime is applicable for this project. Standard day covers daylight operating hours only.
Stated up front so the final cost carries no surprises.
No fuel surcharge applied. Rates are quoted all-in, consistent with OWA's request to remove surcharges.
Sites are prepped and accessible ahead of the crew — any line locates or ground disturbances permits are in place, and lease access maintained for equipment and crew.
IWA requires a minimum of 10 hours of productive field time. With travel to the first site and the last site outside of the 10-hour working time.
No overtime is applicable for this project. The standard day is based on daylight operating hours; hours beyond the standard day are not billed at an overtime rate.
Pricing assumes one cut-and-cap truck/crew at start-up. A second crew is available with a couple days' notice if the schedule requires acceleration.
Standby applies for client-caused delays, wet or frozen access, and regulatory holds outside our control, billed hourly per crew.
How this submission maps to the four weighted categories in the RFQ.

Quotation issued by Scott Bowes · Innovative Well Abandonment